Rehabilitation and Repair projects for FY '15 include:

Sidewalk Replacements   $ 30,000
HVAC Repairs/Replacement   $ 30,000
Street Repairs   $ 70,000
Asbestos Abatement   $ 5,000
Steam Generation & Distribution Upgrades   $ 5,000
Stroup Roof Replacement   $ 250,000
Life Safety Systems Repair & Maintenance   $ 10,000
McCartney Roof Replacement   $ 145,000
Albertson Shingle Replacement   $ 85,000
Rarick 1st Floor VAV Replacement   $ 140,000
MH/CH/Gross Telecom Wiring Replacement   $ 80,000
Akers Energy Center Boiler Replacement Study   $ 10,000
Campus Exterior Lighting Phase 1   $ 930,000
Livestock Pavilion Roof Replacement   $ 300,000
Med Voltage Elec Imp-Phase III, South Campus   $ 150,000
Cunningham Sewer Improvements, Phase I   $ 413,000
Sheridan Shingle Replacement   $ 65,000
Akers Fuel Tank Replacement   $ 418,000
Forsyth Library and Sheridan Hall Roof Repairs   $ 72,000
Malloy Air Handler Replacement   $ 142,284

 

Rehabilitation & Repair Projects for FY '16 include:

Campus Sidewalk Replacements   $ 30,200
HVAC Repairs/Replacement   $ 30,000
Campus Asbestos Abatement   $ 5,000
Steam Generation & Distribution Upgrades   $ 5,000
Life Safety Systems Repairs & Maintenance   $ 15000
Street Repairs   $ 70,000
Campus Carpet Replacement   $ 73,000
Cunningham Hall Expansion Joint Repairs   $ 125,000
Campus Door Hardware Improvements   $ 500,000
Cunningham/Gross Exterior Stair Replacement   $ 55,000
Campus Exterior Lighting Improvements-Ph II   $ 500,000
Cunningham Hall Sewer Improvements-North Zone   $ 250,000
Malloy Hall Ceiling and Light Replacement   $ 230,000
Stair Rails at Gross Coliseum   $ 50,000
Entrance Door Replacement at Cunningham/Gross   $ 160,000
Replace Concrete Paving at Martin Allen Plaza   $ 100,000

 

 

 

 